Overview
Do it right and you get reliable results without adding much to the line cycle. Below: the communication interfaces, fixture design, and where the cycle time actually goes.
PLC Communication
LeakMaster instruments support multiple PLC communication options:
- Discrete I/O: Start, Pass, Fail, Ready signals for simple integration
- Serial (RS-232/485): Full parameter access and data retrieval
- Ethernet/IP: Direct tag access for Allen-Bradley PLCs
- Modbus TCP: Universal Ethernet protocol for any PLC brand
- PROFINET: For Siemens and other PROFINET controllers
Test Fixture Design
The fixture seals the part and plumbs it to the instrument. Three things matter: seal material (has to be compatible with the test medium and the part surface), seal force (enough to stop leaks, not so much it deforms the part), and internal volume (smaller means higher sensitivity and faster tests). Use quick-connect fittings and keep the tubing run between instrument and fixture short.
Cycle Time Optimization
Fill and stabilize eat most of the cycle. Bigger tubing and fittings shorten the fill. For stabilize, control the fill rate so the air heats up less, put regulators close to the fixture, and hold ambient temperature steady. Where you can, overlap the test with part handling to claw back throughput.
Typical applications
- Automotive production lines
- Medical device manufacturing
- Consumer electronics assembly
- HVAC production testing